Capistrano v3 provides a default deploy flow and a rollback flow:
Deploy flow
When you run cap production deploy
, it invokes the following tasks in
sequence:
{% prism ruby %} deploy:starting - start a deployment, make sure everything is ready deploy:started - started hook (for custom tasks) deploy:updating - update server(s) with a new release deploy:updated - updated hook deploy:publishing - publish the new release deploy:published - published hook deploy:finishing - finish the deployment, clean up everything deploy:finished - finished hook {% endprism %}
Notice there are several hook tasks e.g. :started
, :updated
for
you to hook up custom tasks into the flow using after()
and before()
.
Rollback flow
When you run cap production deploy:rollback
, it invokes the following
tasks in sequence:
{% prism ruby %} deploy:starting deploy:started deploy:reverting - revert server(s) to previous release deploy:reverted - reverted hook deploy:publishing deploy:published deploy:finishing_rollback - finish the rollback, clean up everything deploy:finished {% endprism %}
As you can see, rollback flow shares many tasks with deploy flow. But note that, rollback flow runs its own :finishing_rollback
task because its
cleanup process is usually different from deploy flow.
Flow examples
Assume you require the following files in Capfile
,
{% prism ruby %}
Capfile
require 'capistrano/setup' require 'capistrano/deploy' require 'capistrano/bundler' require 'capistrano/rails/migrations' require 'capistrano/rails/assets' {% endprism %}
When you run cap production deploy
, it runs this following tasks:
{% prism ruby %} deploy deploy:starting [before] deploy:ensure_stage deploy:check deploy:started deploy:updating git:create_release deploy:symlink:shared deploy:updated [before] deploy:bundle [after] deploy:migrate deploy:compile_assets deploy:cleanup_assets deploy:normalise_assets deploy:publishing deploy:symlink:release deploy:restart deploy:published deploy:finishing deploy:cleanup deploy:finished deploy:log_revision {% endprism %}
For cap production deploy:rollback
, it runs these tasks:
{% prism ruby %} deploy deploy:starting [before] deploy:ensure_stage deploy:set_shared_assets deploy:check deploy:started deploy:reverting deploy:revert_release deploy:reverted [after] deploy:rollback_assets deploy:publishing deploy:symlink:release deploy:restart deploy:published deploy:finishing_rollback deploy:cleanup_rollback deploy:finished deploy:log_revision {% endprism %}