# Due dates
|
|
|
|
|
|
|
|
> [Introduced][ce-3614] in GitLab 8.7.
|
|
|
|
|
2017-05-08 04:35:38 -04:00
|
|
|
Please read through the [GitLab Issue Documentation](index.md) for an overview on GitLab Issues.
|
|
|
|
|
2017-01-24 08:59:37 -05:00
|
|
|
Due dates can be used in issues to keep track of deadlines and make sure
|
|
|
|
features are shipped on time. Due dates require at least [Reporter permissions][permissions]
|
|
|
|
to be able to edit them. On the contrary, they can be seen by everybody.
|
|
|
|
|
|
|
|
## Setting a due date
|
|
|
|
|
|
|
|
When creating or editing an issue, you can see the due date field from where
|
|
|
|
a calendar will appear to help you choose the date you want. To remove it,
|
|
|
|
select the date text and delete it.
|
|
|
|
|
|
|
|
![Create a due date](img/due_dates_create.png)
|
|
|
|
|
|
|
|
A quicker way to set a due date is via the issue sidebar. Simply expand the
|
|
|
|
sidebar and select **Edit** to pick a due date or remove the existing one.
|
|
|
|
Changes are saved immediately.
|
|
|
|
|
|
|
|
![Edit a due date via the sidebar](img/due_dates_edit_sidebar.png)
|
|
|
|
|
|
|
|
## Making use of due dates
|
|
|
|
|
2017-05-08 04:35:38 -04:00
|
|
|
Issues that have a due date can be distinctively seen in the issue tracker
|
|
|
|
displaying a date next to them. Issues where the date is overdue will have
|
2017-01-24 08:59:37 -05:00
|
|
|
the icon and the date colored red. You can sort issues by those that are
|
|
|
|
_Due soon_ or _Due later_ from the dropdown menu in the right.
|
|
|
|
|
|
|
|
![Issues with due dates in the issues index page](img/due_dates_issues_index_page.png)
|
|
|
|
|
|
|
|
Due dates also appear in your [todos list](../../../workflow/todos.md).
|
|
|
|
|
|
|
|
![Issues with due dates in the todos](img/due_dates_todos.png)
|
|
|
|
|
2018-03-30 09:05:20 -04:00
|
|
|
The day before an open issue is due, an email will be sent to all participants
|
2018-04-10 06:29:40 -04:00
|
|
|
of the issue. Both the due date and the day before are calculated using the
|
|
|
|
server's timezone.
|
2018-03-30 09:05:20 -04:00
|
|
|
|
2018-05-31 10:01:04 -04:00
|
|
|
Issues with due dates can also be exported as an iCalendar feed. The URL of the
|
|
|
|
feed can be added to calendar applications. The feed is accessible by clicking
|
|
|
|
on the _Subscribe to calendar_ button on the following pages:
|
|
|
|
- on the **Assigned Issues** page that is linked on the right-hand side of the
|
|
|
|
GitLab header
|
|
|
|
- on the **Project Issues** page
|
|
|
|
- on the **Group Issues** page
|
|
|
|
|