## Feature Freeze
|
||||
|
||||
On the 7th of each month, the stable branches for the upcoming release will
|
||||
be frozen for major changes. Merge requests may still be merged into master
|
||||
during this period. By freezing the stable branches prior to a release there's
|
||||
no need to worry about last minute merge requests potentially breaking a lot of
|
||||
On the 7th of each month, RC1 of the upcoming release is released and the stable branch for this release is frozen, which means master is no longer merged into it.
|
||||
Merge requests may still be merged into master during this period,
|
||||
but they will go into the _next_ release, unless they are manually cherry-picked into the stable branch.
|
||||
By freezing the stable branches prior to a release there's no need to worry
|
||||
about last minute merge requests potentially breaking a lot of
|
||||
things.
|
||||
|
||||
What is considered to be a major change is determined on a case by case basis as
|
||||
this definition depends very much on the context of changes. For example, a 5
|
||||
line change might have a big impact on the entire application. Ultimately the
|
||||
decision will be made by the maintainers and the release managers.
|
||||
Once the stable branch is frozen, only fixes for regressions (bugs introduced in that same release) and security issues will be cherry-picked into the stable branch, and released in the next RC (before the 22nd) or patch release (after the 22nd).
|
||||
|
||||
If your merge request does not meet that requirement but you still think it should go into the upcoming release,
|
||||
you can ask for an exception to be made.
|
||||
To make sure the advantages and disadvantages are well considered, exceptions require sign-off from 3 people besides the developer: a Release Manager, the relevant engineering lead, and an engineering director, VP, or CTO.
|
||||
|
||||
You and they should weigh the benefit and urgency of the change (how important it is to the company that this is released _right now_ instead of in a month)
|
||||
against the potential negative impact (things breaking without enough time to comfortably find them and fix them before the release on the 22nd).
|
||||
When in doubt, we err on the side of _not_ cherry-picking.
|
||||
|
||||
For example, an exception may be made for a trivial 1-5 line performance improvement
|
||||
(e.g. adding an index or adding `includes` to a query), but not for a new feature, no matter how relatively small or thoroughly tested.
|
||||
|
||||
During the feature freeze all merge requests that are meant to go into the upcoming
|
||||
release should have the correct milestone assigned _and_ have the label
|
||||
~"Pick into Stable" set. Merge requests without a milestone and this label will
|
||||
~"Pick into Stable" set, so that release managers can find and pick them.
|
||||
Merge requests without a milestone and this label will
|
||||
not be merged into any stable branches.
|
||||
|
||||
## Copy & paste responses
|
||||
|
|