Merge branch 'fix-time-sensitive-helper-spec' into 'master'
Fix time-sensitive helper spec See merge request !10046
This commit is contained in:
commit
bb1620aaf7
1 changed files with 10 additions and 6 deletions
|
@ -49,8 +49,12 @@ describe MilestonesHelper do
|
|||
end
|
||||
|
||||
describe '#milestone_remaining_days' do
|
||||
around do |example|
|
||||
Timecop.freeze(Time.utc(2017, 3, 17)) { example.run }
|
||||
end
|
||||
|
||||
context 'when less than 31 days remaining' do
|
||||
let(:milestone_remaining) { milestone_remaining_days(build_stubbed(:milestone, due_date: 12.2.days.from_now)) }
|
||||
let(:milestone_remaining) { milestone_remaining_days(build_stubbed(:milestone, due_date: 12.days.from_now.utc)) }
|
||||
|
||||
it 'returns days remaining' do
|
||||
expect(milestone_remaining).to eq("<strong>12</strong> days remaining")
|
||||
|
@ -58,7 +62,7 @@ describe MilestonesHelper do
|
|||
end
|
||||
|
||||
context 'when less than 1 year and more than 30 days remaining' do
|
||||
let(:milestone_remaining) { milestone_remaining_days(build_stubbed(:milestone, due_date: 2.months.from_now)) }
|
||||
let(:milestone_remaining) { milestone_remaining_days(build_stubbed(:milestone, due_date: 2.months.from_now.utc)) }
|
||||
|
||||
it 'returns months remaining' do
|
||||
expect(milestone_remaining).to eq("<strong>2</strong> months remaining")
|
||||
|
@ -66,7 +70,7 @@ describe MilestonesHelper do
|
|||
end
|
||||
|
||||
context 'when more than 1 year remaining' do
|
||||
let(:milestone_remaining) { milestone_remaining_days(build_stubbed(:milestone, due_date: 1.year.from_now + 2.days)) }
|
||||
let(:milestone_remaining) { milestone_remaining_days(build_stubbed(:milestone, due_date: (1.year.from_now + 2.days).utc)) }
|
||||
|
||||
it 'returns years remaining' do
|
||||
expect(milestone_remaining).to eq("<strong>1</strong> year remaining")
|
||||
|
@ -74,7 +78,7 @@ describe MilestonesHelper do
|
|||
end
|
||||
|
||||
context 'when milestone is expired' do
|
||||
let(:milestone_remaining) { milestone_remaining_days(build_stubbed(:milestone, due_date: 2.days.ago)) }
|
||||
let(:milestone_remaining) { milestone_remaining_days(build_stubbed(:milestone, due_date: 2.days.ago.utc)) }
|
||||
|
||||
it 'returns "Past due"' do
|
||||
expect(milestone_remaining).to eq("<strong>Past due</strong>")
|
||||
|
@ -82,7 +86,7 @@ describe MilestonesHelper do
|
|||
end
|
||||
|
||||
context 'when milestone has start_date in the future' do
|
||||
let(:milestone_remaining) { milestone_remaining_days(build_stubbed(:milestone, start_date: 2.days.from_now)) }
|
||||
let(:milestone_remaining) { milestone_remaining_days(build_stubbed(:milestone, start_date: 2.days.from_now.utc)) }
|
||||
|
||||
it 'returns "Upcoming"' do
|
||||
expect(milestone_remaining).to eq("<strong>Upcoming</strong>")
|
||||
|
@ -90,7 +94,7 @@ describe MilestonesHelper do
|
|||
end
|
||||
|
||||
context 'when milestone has start_date in the past' do
|
||||
let(:milestone_remaining) { milestone_remaining_days(build_stubbed(:milestone, start_date: 2.days.ago)) }
|
||||
let(:milestone_remaining) { milestone_remaining_days(build_stubbed(:milestone, start_date: 2.days.ago.utc)) }
|
||||
|
||||
it 'returns days elapsed' do
|
||||
expect(milestone_remaining).to eq("<strong>2</strong> days elapsed")
|
||||
|
|
Loading…
Reference in a new issue