# Docker Release Process
 | 
						||
 | 
						||
This document describes how the Docker project is released. The Docker project
 | 
						||
release process targets the Engine, Compose, Kitematic, Machine, Swarm,
 | 
						||
Distribution, Notary and their underlying dependencies (libnetwork, libkv,
 | 
						||
etc...).
 | 
						||
 | 
						||
Step-by-step technical details of the process are described in 
 | 
						||
[RELEASE-CHECKLIST.md](https://github.com/docker/docker/blob/master/project/RELEASE-CHECKLIST.md).
 | 
						||
 | 
						||
## Release cycle
 | 
						||
 | 
						||
The Docker project follows a **time-based release cycle** and ships every nine
 | 
						||
weeks. A release cycle starts the same day the previous release cycle ends.
 | 
						||
 | 
						||
The first six weeks of the cycle are dedicated to development and review. During
 | 
						||
this phase, new features and bugfixes submitted to any of the projects are
 | 
						||
**eligible** to be shipped as part of the next release. No changeset submitted
 | 
						||
during this period is however guaranteed to be merged for the current release
 | 
						||
cycle.
 | 
						||
 | 
						||
## The freeze period
 | 
						||
 | 
						||
Six weeks after the beginning of the cycle, the codebase is officially frozen
 | 
						||
and the codebase reaches a state close to the final release. A Release Candidate
 | 
						||
(RC) gets created at the same time. The freeze period is used to find bugs and
 | 
						||
get feedback on the state of the RC before the release.
 | 
						||
 | 
						||
During this freeze period, while the `master` branch will continue its normal
 | 
						||
development cycle, no new features are accepted into the RC. As bugs are fixed
 | 
						||
in `master` the release owner will selectively 'cherry-pick' critical ones to
 | 
						||
be included into the RC. As the RC changes, new ones are made available for the
 | 
						||
community to test and review.
 | 
						||
 | 
						||
This period lasts for three weeks.
 | 
						||
 | 
						||
## How to maximize chances of being merged before the freeze date?
 | 
						||
 | 
						||
First of all, there is never a guarantee that a specific changeset is going to
 | 
						||
be merged. However there are different actions to follow to maximize the chances
 | 
						||
for a changeset to be merged:
 | 
						||
 | 
						||
- The team gives priority to review the PRs aligned with the Roadmap (usually
 | 
						||
defined by a ROADMAP.md file at the root of the repository).
 | 
						||
- The earlier a PR is opened, the more time the maintainers have to review. For
 | 
						||
example, if a PR is opened the day before the freeze date, it’s very unlikely
 | 
						||
that it will be merged for the release.
 | 
						||
- Constant communication with the maintainers (mailing-list, IRC, GitHub issues,
 | 
						||
etc.) allows to get early feedback on the design before getting into the
 | 
						||
implementation, which usually reduces the time needed to discuss a changeset.
 | 
						||
- If the code is commented, fully tested and by extension follows every single
 | 
						||
rules defined by the [CONTRIBUTING guide](
 | 
						||
https://github.com/docker/docker/blob/master/CONTRIBUTING.md), this will help
 | 
						||
the maintainers by speeding up the review.
 | 
						||
 | 
						||
## The release
 | 
						||
 | 
						||
At the end of the freeze (nine weeks after the start of the cycle), all the
 | 
						||
projects are released together.
 | 
						||
 | 
						||
```
 | 
						||
                                        Codebase              Release
 | 
						||
Start of                                is frozen             (end of the
 | 
						||
the Cycle                               (7th week)            9th week)
 | 
						||
+---------------------------------------+---------------------+
 | 
						||
|                                       |                     |
 | 
						||
|           Development phase           |    Freeze phase     |
 | 
						||
|                                       |                     |
 | 
						||
+---------------------------------------+---------------------+
 | 
						||
                   6 weeks                      3 weeks
 | 
						||
<---------------------------------------><-------------------->
 | 
						||
```
 | 
						||
 | 
						||
## Exceptions
 | 
						||
 | 
						||
If a critical issue is found at the end of the freeze period and more time is
 | 
						||
needed to address it, the release will be pushed back. When a release gets
 | 
						||
pushed back, the next release cycle gets delayed as well.
 |